Project update 13th June 2011

13th June 2011
“The construction of the new 620Sq M building extension is completed, the completion of the finished goods point of release function will now commence. Development of this point of release bay will then enable JH Lavender to continue with their manufacturing reconfiguration plans within the main plant”
(click photo to enlarge)

Project update 6th June 2011

6th June 2011

“The external construction of the building extension is completed, and the installation of the internal services has commenced”