This investment program includes the creation of a new die casting hall, installation of a Colosio closed loop 1600T automated diecasting cell and additional alloy melting facility.
The building extension also enables the re-location of the die making function and the re-alignment of the existing gravity foundry.
On completion of this stage of the extension a further construction project commences for a new fully enclosed storage and component despatch function.

“The machine bases are now complete and the creation of the pit side walls and service ducting is underway”
(click photo to enlarge)

“Despite the challenges set by the weather, the construction remains on track to the timing plan. Additional weather protection material has been laid to protect the concrete previously laid”
(click photo to enlarge)

“The 3x machine pits are now excavated with the bases and service trenches installed. The tool room floor is now as prepared for concreting. The service supplies for water, electricity and cooling systems have been relocated to the new locations”.
(click photo to enlarge)

“The foundation base has been completed, and the construction stages have commenced with the footings and preparation for the main building fabric construction”.
(click photo to enlarge)