JH Lavender & Co Ltd - Investment April 2011



Project update 29th April 2011

29th April 2011

“The steel frame work is completed for the new building extension, enabling the next stage of construction with the roofing and side cladding to be added to the new fully enclosed point of release bay”
(click photo to enlarge)

Project update 18th April 2011

18th April 2011

“The base is completed, and the erection phase for the structural steelwork will commence. The construction is currently running 1 week ahead of the timing plan agreed with the construction contractors”
(click photo to enlarge)

Project update 11th April 2011

11th April 2011

“The concrete is pumped on to the prepared foundations to create the base for the internal section of the building extension”
(click photo to enlarge)


Project update 4th April 2011

4th April 2011

“The construction phase is underway, with the footings completed and the bases laid ready for the erection of the steel supporting structure”
(click photo to enlarge)